One Excellent Job Leads To Another

Berenice Naval Base ShoreBox Installation

media
Berenice Naval Base ShoreBox Installation

Strategic Naval Infrastructure Upgrade

Scope of Work

Custom Schneider ShoreBox System
  • 440V/60Hz power conversion
  • 9 hotel service connections (400A each)
  • Integrated safety interlocks
Remote Site Challenges Addressed
  • Desert climate hardening (55°C rated)
  • Sand filtration for cooling systems
  • Corrosion-resistant marine coatings

Technical Specifications

Component Specifications & Benefits

Component Specification Benefit
Power Modules 2.5MW capacity Supports aircraft carriers
Control System Automated load sharing Prevents overloads
Safety Features IP56 enclosure Storm/dust protection

Innovations

  • Pre-fabricated cable ramps for rapid deployment
  • Dual-fuel backup capability

Operational Impact

  • Emissions: Eliminated 900 tons of CO2 annually
  • Reliability: Zero service interruptions since commissioning

Information About the Project

Location Berenice Naval Base,
Alexandria, Egypt
End-User Egyptian Navy
Award Date May 2019
Contract W912ER19-P-0019