One Excellent Job Leads To Another

Critical Generator Spare Parts Procurement

media
Critical Generator Spare Parts Procurement

Project Objective

To ensure continuous operation of strategic mobile hybrid power generators through timely procurement of mission-critical spare parts.

Procurement Details

Key Components Sourced

  • Engine System: Pistons, turbochargers, fuel injectors
  • Electrical System: Voltage regulators, control modules
  • Hybrid Components: Battery packs, power converters
  • Structural Parts: Shock-mounted enclosures, cooling fans

Quality Assurance

  • OEM-certified components only
  • 100% pre-shipment inspection
  • MIL-STD-130N marking compliance

Technical Specifications

Component Procurement Matrix

Component Type Quantity Compatibility Lead Time
Diesel Engine Kits 12 HDG-4000 Series 3 weeks
Power Electronics 8 400Hz Output 2 weeks
Cooling Systems 5 Desert Climate 4 weeks

Execution Highlights

Supply Chain Management

  • Established emergency air freight channels
  • Dual-source procurement for critical items

End-User Benefits

  • Reduced generator downtime by 75%
  • Extended equipment service life by 5+ years
  • Maintained 100% power availability for armament systems

Information About the Project

Location Power Generators
Workshop, Almaza
End-User Egyptian Armament & Ammunition Department
Award Date March 2020
Contract W912ER-20-C-0012