One Excellent Job Leads To Another

Emergency Structural Repairs for Egyptian Navy Facilities

media
Emergency Structural Repairs for Egyptian Navy Facilities

Critical Repairs Executed

Buildings Addressed: #41, #43, #45, #46

Deficiency Analysis & Solutions

Deficiency Solution Implemented Safety Impact
Roof leaks Full membrane replacement Eliminated water damage risks
Skylight failures Impact-resistant glazing Improved natural lighting/safety
Structural cracks Carbon fiber reinforcement Restored load-bearing capacity
Faulty electrical LED fixture replacements Reduced fire hazards by 90%

Project Execution

Phased Approach

  • Phase I: Emergency containment (temporary seals/lighting)
  • Phase II: Roofing/skylight replacements (completed during low-tide periods)
  • Phase III: Structural reinforcements (non-intrusive carbon fiber application)

Key Achievement: Zero operational disruptions during repairs

Performance Metrics

  • Timeliness: All repairs completed in 55 days (25% ahead of schedule)
  • Cost Efficiency: 18% under budget through value engineering
  • Quality: Zero callbacks post-repair

Information About the Project

Location Ras El-Tin Naval Base,
Alexandria, Egypt
End-User Egyptian Navy
Award Date November 2020
Contract W912ER-21-C-0003