One Excellent Job Leads To Another

Submarine Workshop Modernization

media
Submarine Workshop Modernization

Strategic Renovation Scope

Core Upgrades Implemented

System Upgrade Details Military Standard
Material Handling 3-ton overhead crane with remote control NATO STANAG 4101
Flooring 1,575 sq ft epoxy-coated concrete slab MIL-STD-810G shock resistance
Power Systems Tri-frequency network (400Hz/60Hz/50Hz) IEEE 45 marine electrical
Support Systems Explosion-proof lighting & ATEX ventilation NFPA 70E

Execution Highlights

Phased Implementation

1. Structural
  • Demolished and degraded slab using precision saw-cutting
  • Installed reinforced concrete with vibration-dampening additives
2. Mechanical
  • Crane rail alignment to ±1mm tolerance
  • Compressed air piping with moisture traps
3. Electrical
  • Frequency converter banks for weapon system testing
  • Grounding grid with <2-ohm resistance

Innovative Solutions

  • Used BIM modeling to coordinate multi-trade installations
  • Night shifts maintained 50% workshop capacity during upgrades

Technical Specifications

Component Performance Matrix

Component Key Feature Performance Gain
Crane System 5-ton safety factor 40% faster torpedo handling
Epoxy Floor Chemical-resistant Withstands acid spills
HVAC HEPA filtration Meets submarine air quality specs

Project Outcomes

  • Weapons Compatibility: Full compliance with US Navy SSBN maintenance standards
  • Efficiency: Reduced weapon turnaround time by 35%
  • Safety: Zero electrical incidents since commissioning

Information About the Project

Location Ras El-Tin Naval Base,
Alexandria, Egypt
End-User Egyptian Navy
Award Date October 2019
Contract W912ER-20-C-0001